top of page

September 2024 U.S. Offshore Wind Update

Wiki-Wind

Updated: Oct 3, 2024


WHAT’S INSIDE


  • Construction Updates - Progress updates on active U.S. Offshore Wind construction

  • Vessels - Updates on newbuilds and featured vessels

  • Speed Read - One-liners on significant events


Construction Updates


Coastal Virginia Offshore Wind (CVOW)

  • Seventy-seven (77) monopiles have been installed by the ORION as of September 24. Foundation installation is complete for 2024 and will resume May 1, 2025.

  • Unexploded Ordinance (UXO) relocation is ongoing along the export cable corridor.

  • Cable installation vessel LIVING STONE is preparing for export cable installation.


Revolution Wind

  • Fifty-two (52) monopiles have been installed as of September 30.

  • Four (4) wind turbine generators have been installed as of September 30.

  • Wind Turbine Installation Vessel (WTIV) SCYLLA is installing wind turbine generator components.

  • The BOKALIFT 2 is installing monopile foundations while the BOKALIFT 1 installs secondary steel at existing foundations.

  • SEAWAY AIMERY is performing inter-array cable (IAC) installation.

  • J.D. Assister is performing post-IAC burial.

  • PAUL CANDIES is performing wind turbine commissioning.


South Fork Wind

  • Wind turbine installation and commissioning is complete is complete.


Vineyard Wind

  • Twenty-nine (29) out of sixty-two (62) complete wind turbines have been installed as of September 24.

  • Forty-seven (47) out of sixty-two (62) monopiles have been installed as of September 24.

  • Forty-seven (47) out of sixty-two (62) transition pieces have been installed as of August 20.

  • The trenching support vessel (TSV) SYMPHONY is on scene performing post cable burial for the Vineyard Wind inter-array cable.

  • The cable installation vessel (CSV) CONNECTOR is on scene performing inter-array cable installation.

  • Wind Turbine Installation Vessel (WTIV) SEA INSTALLER is on scene installing wind turbine generator components.


See more market intelligence on U.S. Offshore Wind projects from the Wiki Wind Open Source Database. Find it here:


Vessels

  • No update


Visit the Wiki Wind Vessel Register to see more U.S. Offshore Wind Vessels. Find it here: https://www.wikiwind.us/vessels


Speed Read

  • The Bureau of Ocean Energy Management (BOEM) granted record of decision (ROD) for US Wind’s Maryland Offshore Wind Project which included joint approval of their commercial operation plan (COP).

  • Equinor placed an order with Vestas for fifty-four (54) 15-megawatt (MW) V236-15.0 wind turbines for the Empire Wind 1 project in New York.

 
 
 