
WHAT’S INSIDE
Construction Updates - Progress updates on active U.S. Offshore Wind construction
Vessels - Updates on newbuilds and featured vessels
Speed Read - One-liners on significant events
Construction Updates
Coastal Virginia Offshore Wind (CVOW)
Seventy-seven (77) out of 176 monopiles have been installed by the ORION as of September 24. Foundation installation is complete for 2024 and will resume May 1, 2025.
Unexploded Ordinance (UXO) relocation is ongoing along the export cable corridor.
Cable installation vessel LIVING STONE is performing export cable installation.
Rock installation vessel FLINTSTONE will return to perform scour protection installation.
Revolution Wind
Wind Turbine Installation Vessel (WTIV) SCYLLA is installing wind turbine generator components.
The BOKALIFT 2 is installing monopile foundations while the BOKALIFT 1 installs secondary steel at existing foundations.
SEAWAY AIMERY is performing inter-array cable (IAC) installation.
J.D. ASSISTER is performing post-IAC trenching.
PAUL CANDIES is performing wind turbine commissioning.
NEXANS AURORA is performing export cable installation.
DEEP CYGNUS is performing export able pre-lay survey and post-lay trenching.
HEA LEVIATHAN is performing offshore substation (OSS) commissioning.
South Fork Wind
Wind turbine installation and commissioning is complete.
Vineyard Wind
Twenty-four (24)Â out of sixty-two (62) complete wind turbines have been installed as of October 22.
Thirty-two (32) out of sixty-two (62) tower sections have been installed as of October 22.
Forty-seven (47)Â out of sixty-two (62) transition pieces have been installed as of October 22.
Forty-seven (47)Â out of sixty-two (62) monopiles have been installed as of October 22.
Foundation installation vessel ORION is performing monopile installation with the SEA CHALLENGER to follow performing transition piece installation.
Wind Turbine Installation Vessel (WTIV) SEA INSTALLER is on scene installing wind turbine generator components.
See more market intelligence on U.S. Offshore Wind projects from the Wiki Wind Open Source Database. Find it here:
Vessels
No update
Visit the Wiki Wind Vessel Register to see more U.S. Offshore Wind Vessels. Find it here: https://www.wikiwind.us/vessels
Speed Read
The Bureau of Ocean Energy Management (BOEM) approved the construction and operations plan (COP) for Atlantic Shores South projects 1 and 2.
Equinor announced Patriot Offshore as the preferred CTV supplier for Empire Wind project.
Leading Light Wind awarded Hellenic Cables for the supply of 65km of 132kV inter-array cable (IAC) with a 2030 delivery for its New Jersey project.
Dominion Energy finalized the sale of 50% non-controlling interest in its Coastal Virginia Offshore Wind (CVOW) project to investment firm, Stonepeak.
SouthCoast Wind 1, received state approvals for the construction and operation of onshore transmission facilities at Brayton Point in Somerset, MA.
Dominion Energy finalized the purchase of the Kitty Hawk North offshore wind lease area from Avangrid for approximately US$ 160 million.
Four developers submitted bids into New York's fifth offshore wind solicitation. Those bidders included
Orsted: 1,485 MW, Long Island Wind (combination of Sunrise and Starboard Wind)
RWE and National Grid Ventures: 2,800 MW, Community Wind (increase from 1,314 MW previous bid)
Vineyard Offshore: 1,350 MW, Excelsior Wind
TotalEnergies, Rise Light & Power and Corio Generation: 1,365 MW, Attentive Energy One
BOEM announced the provisional winners of the Gulf of Maine Offshore Wind Energy Lease Sale which included Invenergy and Avangrid. The award totals 6.8 GW and US$ 21.9 million sale proceeds.
Comments